These are not quotes.

1. Finally getting to the end as far as the FEMA paperwork is concerned.
- Just a couple more worksheets to finish up.
- A big one is the debris removal.
- We get a buck a yard for burning everything that is out there, (there are 10,000 yards)
- How much have we got to borrow?
- 300K

2. …on the electric side of things
- There is nothing being questioned by FEMA anymore.
- Basically, we file 2 project worksheets. 1 for work to date, and one for future work.
- According to city administrator, Lake View will qualify for upsizing conductors.
- Conductor replacement really means rebuilding the whole line.
- It all happens in the next 3 or 4 weeks.
- When the plans are submitted, isn’t it reviewed?
- Not guaranteed until it goes through another board.

3. Difference between 404 and 406 program.
- 404 funding may provide $20,000 for engineering costs.
- It’s looking pretty positive.