Your Ad Here

VIDEO - East Sac County school boards doubling number of lights at Wall Lake football field, having tough time getting gym painted (PPEL Projects report)




1. New doors.

2. Repair at the Sac Elem parking lot.
- $63K.

3. Track to be looked at for repair.
- Asphalt is showing in some places.
- Original installers called in…

4. Stage curtains replaced in Sac.
- two to go.

5. Painting in Sac cafeteria and gym.
- going to be difficult to paint gym (ceiling, etc)
- Window of opportunity to get it done closing.
- Scope of job making it difficult to get quotes.


6. Hail damage.

7. Baseball-softball field lights in Wall Lake.

8. New roof on Lake View buildings.

9. Debris clean-up, FEMA reimbursement.
- FEMA will pick up 85% of cost.

10. Fence cover on baseball-softball field.


11. Football field lights.
- Not dented up because the covers are made of a cast material.
- Insurance company report says no damage to lights.
-November 2008 candle foot reading was 28.85. After hail storm the candle foot reading was 13.65.
- There may be an abbreviated settlement. (possibly no more than $10K)
- 2 bids for total light replacement: Musco lighting - $130K, BLI Lighting - $67k.
- BLI Lighting gets the work.


12. FPS renovation.
- Stalled.
- going to wait until after next year’s classes let out.
- Too much dust, noise, confusion to do work while trying to conduct classes.

13. New skid loader to be purchased for Lake View.
- Primarily used for snow removal.
- Will have own buckets.
- Private volunteer letting school down.
- will be used year round.
- Motion to purchase approved.



Copyright (c)2007-2010 Curtis Bloes All Rights Reserved