Why you want to view: This will cost more than was budgeted
LAKE VIEW, IOWA – MARCH 21, 2011
Bill Leners, Lake View’s Electric Superintendent, has determined which lines in the Lake View area could use some attention.
The cost of this project is estimated at $140,000 with roughly $90,000 going for labor and $50,000 for materials.
The city budgeted $50,000 over the next two years for both overhead and underground line replacement, with the cost of materials budgeted as inventory purchases.
he council directed Leners to go get bids for the electrical project with the understanding that they have the right to reject any and all bids should they determine that they don’t want to spend that much money. According to Leners, the bids may be in as soon as April 1.
032111LVCCDOC0002
032111LVCCDOC0003
- The final FEMA payment is still sitting on a desk in Kansas City.
Copyright (c)2007-2011 TheSacNews.com Inc. All Rights Reserved
Subscribe to:
Post Comments (Atom)
Top 10 Posts
- Nick Sippel of Schaller, Iowa Shot by Law Enforcement in Sac County, Iowa
- Sac City Council approves resolution of support for Loring Hospital
- Sen. Grassley Roundup
- UPDATED: Sac County Sheriff's Department looking for anyone with information about man found dead in car in Early, Iowa
- Frustrated residents teach the Mayor of Sac City, Iowa that throwing more laws at the problem doesn’t work… (She still considers enacting more laws)
- Sac County Traffic Charges Disposed Between August 9, 2011 and August 15, 2011
- Sioux City Woman Sentenced to 9 Days, 12 Hours, 45 Minutes for Driving While Suspended
- Sac City Council Pays bills for Waste Water Treatment Plant Project
- February 14, 2011 Sac City Council Agenda
- Notice of Death - Edward Pickhinke
No comments:
Post a Comment